Land adjacent to Bramleymoor Lane, near Marsh Lane (East Midlands)

loading

Update Aug 2021 Permission for this site has now lapsed. No work has been carried out since permission was granted. Read more…

Update Dec 2018 Permission for this site has been granted by a planning inspector. Read more…

Fracking company Ineos Upstream have submitted a planning application for a shale gas exploration site on fields to the west of Bramleymoor Lane, near Marsh Lane, Derbyshire.

You can object to this application >>here<<

An example objection letter can be downloaded >>here<<
(The letter is specific to Ineos’s Harthill site but the points can be modified easily)

Planning Applications

Click on the column headers to reorder table columns.

Licensee Planning ID Notes Submitted Decision Status Consultation
IneosCM4/0517/10Construction of a well site and creation of a new access track, mobilisation of drilling, ancillary equipment and contractor welfare facilities to drill a vertical hydrocarbon exploratory core well and mobilisation of workover rig, listening well operations, and retention of the site and wellhead assembly gear for a temporary period of 5 years on land adjacent to Bramleymoor Lane, near Marsh Lane.08/05/201716/08/2018GrantedClosed

Environmental Permits

Click on the column headers to reorder table columns.

Licensee Permit ID Notes Comments open Comments deadline Status Consultation
IneosEPR/FB3109FG/A001Application from INEOS Upstream Limited for a Standard Rules Mining Waste Permit to manage waste from drilling an exploratory borehole to take core samples of the rock at Bramleymoor Lane site25/05/201722/06/2017Pre-planningClosed